ABC Contractors
Sample Report — General Contractor

GC Daily Report

See how our GC daily reports track subcontractor trades, project status, quality control, coordination, inspections, and more — everything a general contractor needs to document on a commercial project.

Trades On Site

9 active

52 workers

Equipment

9 pieces

across 5 trades

Inspections

4 today

All passed

Safety

0 incidents

Clean day

Report Information

Project

Meridian Tower — Mixed-Use Development

Project #

GC-2026-1185

Date

Wednesday, June 3, 2026

Status

Final

Location

Atlanta, GA — 245 Peachtree Center Ave NE

Owner/Client

Meridian Capital Partners LLC

General Contractor

ABC Contractors

Prepared By

Steven Walsh

Superintendent

Ray Delgado

Project Manager

Karen Nguyen

Shift

6:30 AM - 5:00 PM

Weather

Partly Cloudy · 88°F / 68°F

Overall Project Status

Project Phase

Superstructure

% Complete

42%

Active Trades

9

Total Workforce

62

Major Activities Today

• Structural steel erection continued on floors 8–10 — 22 tons set today. • Concrete deck pour completed on Level 7 (4,200 SF, 85 CY). • MEP rough-in progressing on floors 3–5, electrical conduit and plumbing risers. • Curtain wall installation began on the south elevation, floors 2–4.

Key Milestones

• Level 7 deck pour complete — opens path for steel on floors 11–12 next week. • Curtain wall south elevation kick-off on schedule. • Elevator shaft core walls cured and ready for guide rail installation.

Critical Path Items

• Steel erection floors 8–12 (2 weeks behind original, recovery plan in effect). • Curtain wall delivery for north elevation — lead time 6 weeks, procurement tracking. • Fire protection rough-in must follow MEP by no more than 2 floors.

Upcoming Activities

• Tower crane inspection scheduled for Friday, June 5. • Level 8 deck forming to begin Thursday. • Waterproofing crew mobilizing for below-grade parking structure.

Subcontractor Trades
10 trades · 52 workers · 10 supers · 9 equip

TradeCompanyWorkersSupersEquipStatusLocationWork Description
Structural SteelIronworks Southeast LLC1223
Active
Floors 8–10, North & East baysSet 22 tons structural steel. Bolted connections torqued and inspected per AISC 360. Tower crane utilized for all picks.
ConcretePeach State Concrete812
Active
Level 7 deckPoured 85 CY of 5000 psi concrete for Level 7 suspended deck. Pump truck on site 7:00 AM – 12:00 PM. Finishing and curing compound applied.
ElectricalTri-County Electric Inc.61
Active
Floors 3–5 core & tenant spacesRan EMT and rigid conduit through floors 3–5. Installed junction boxes at column lines per electrical plan E-301.
PlumbingMetro Mechanical Services511
Active
Tower A core, floors 3–5Installed 4 waste risers and 2 vent stacks. Tested existing risers on floor 2 — passed pressure test at 50 psi.
HVACMetro Mechanical Services41
Active
Floors 3–4Hung main ductwork on floor 3. Resolved routing conflict at column B-6 per RFI-0089 — rerouted above plumbing.
Glazing/Curtain WallApex Facade Systems612
Active
South elevation, floors 2–4Began mullion installation — set 18 mullion sections and 6 transom bars. Anchor bolt placement verified against shop drawings.
Drywall/Metal StudsInterior Concepts LLC41
Active
Floor 1 lobby & common areasCompleted metal stud framing for lobby walls — 1,200 SF. Layout verified against architectural plans.
WaterproofingSealPro Waterproofing31
Active
Tower A elevator pitApplied second coat of waterproofing membrane. First coat cured and passed adhesion test. Awaiting 24-hr cure before flood test.
Fire ProtectionSouthern Fire Systems411
Active
Floor 3Continued fire sprinkler rough-in on floor 3. Hung 280 LF of main/branch piping. Coordinating with HVAC for ceiling space allocation.
Earthwork/SiteworkGrading Solutions Inc.00
On Hold
Exterior siteOn hold pending building envelope completion. Mobilization scheduled for Phase 2 site work in August.
Totals52109

Equipment Summary
9 total pieces

TradeCompany# Equipment
Structural SteelIronworks Southeast LLC3
ConcretePeach State Concrete2
PlumbingMetro Mechanical Services1
Glazing/Curtain WallApex Facade Systems2
Fire ProtectionSouthern Fire Systems1
Total9

Inspections
4 inspections

TypeResultAgencyInspectorAreaNotes
Structural Steel — Bolted Connections
Pass
Smith & Associates SEGreg Palmer, P.E.Floor 7 connectionsAll torque values within AISC 360 spec. DTI washers verified.
Concrete — Pre-Pour
Pass
City of Atlanta Building Dept.Maria SantosLevel 7 deckRebar placement, cover, and shoring verified per structural drawings S-701. Approved for pour.
Fireproofing Thickness
Pass
ABC Contractors (QC)Steven WalshFloor 4 columnsAll readings above minimum 1.5" per spec Section 07 81 00. Average 1.72".
Erosion Control / SWPPP
Pass
Dawson County EnvironmentalAngela TorresPerimeter & washoutAll BMPs functional. Washout area at 60% — cleanout scheduled Thursday.

Quality Control

• Concrete cylinders taken from Level 7 pour — 3 sets, 7-day and 28-day breaks scheduled. • Steel bolt torque verification completed on floor 7 connections — all within spec (AISC 360). • Curtain wall anchor bolt placement checked against shop drawings — 2 anchors out of tolerance on grid line C, corrected same day. • Fireproofing thickness tested on floor 4 columns — all readings above minimum 1.5" per spec.

Coordination Issues

• MEP coordination meeting held at 7:00 AM — resolved HVAC duct routing conflict at floor 4 column line B-6. HVAC rerouted above plumbing per RFI-0089. • Elevator contractor (ThyssenKrupp) confirmed guide rail delivery for June 15 — aligns with core wall completion. • Curtain wall installer and structural steel erector established clearance zones to avoid concurrent overhead work on south elevation.

Environmental Compliance

• Stormwater pollution prevention plan (SWPPP) inspection completed — all BMPs in good condition. • Silt fence along Peachtree Center Ave intact, no sediment discharge observed. • Concrete washout area inspected — containment liner holding, 60% capacity. Scheduled for cleanout Thursday. • Noise monitoring at property line — peak reading 78 dB at 2:15 PM during steel erection, within city permit limit of 85 dB.

Safety
0 incidents — Clean day

No safety incidents reported today

All trades compliant with site safety plan. Daily toolbox talks conducted by each trade foreman.

Visitors
3 visitors

Owner
James Whitfield — Meridian Capital Partners
Monthly progress walk with PM Karen Nguyen. Reviewed curtain wall mock-up, inspected Level 7 deck pour in progress. Pleased with progress and quality. Requested updated schedule showing steel recovery plan.
Architect
Lisa Chang, AIA — HKS Architects
Reviewed lobby layout framing against design intent drawings. Confirmed ceiling heights and soffit locations for floors 1–2. Minor RFI to follow regarding storefront head detail at main entrance.
Inspection Staff
Maria Santos — City of Atlanta
Pre-pour inspection of Level 7 deck. Approved rebar placement and shoring. No deficiencies noted.

Field Directed Changes
2 directives

Architect
Lisa Chang, AIA — HKS Architects
Directed addition of blocking for future signage attachment at lobby storefront head, grid line 3 between A and B. Verbal authorization pending formal ASI.
EOR
Tom Reeves, P.E. — Walter P Moore
Approved field modification to steel connection detail at floor 9, grid line D-7. Substituted bolted connection for originally specified welded connection due to field access constraints. No structural impact per EOR review.

Material Received
4 deliveries

MaterialQtyUnitSupplierTicket #Received ByStorageSubmittalPO QtyNotes
Structural Steel — W-shapes & plates22TonsNucor Steel — BirminghamNS-44190R. DelgadoTower crane staging areaCompliantMatchMill certs reviewed and filed
Ready Mix Concrete (5000 psi)85CYThomas Concrete — AtlantaTC-91205S. WalshDirect pour — Level 7 deckCompliantMatchSlump: 5.0", Air: 5.2%, Temp: 74°F. 3 sets cylinders taken.
Curtain Wall Mullions — Aluminum24EAKawneer — Bloomsburg, PAKW-78341Apex Facade foremanSecured laydown — south lotCompliantVariance

PO was for 30 units. Remaining 6 on backorder, ETA June 10.

Finish verified — Dark Bronze anodized per spec 08 44 13
EMT Conduit — 3/4" & 1"2,400LFGraybar Electric — AtlantaGB-55102Tri-County elec. foremanFloor 3 stagingCompliantMatch

Work In Progress

• Structural steel erection — floors 8–10, north and east bays. • Concrete deck forming and shoring — Level 8 prep underway. • MEP rough-in — electrical conduit, plumbing waste/vent risers on floors 3–5. • Curtain wall framing — south elevation, floors 2–4 mullion installation. • Elevator pit waterproofing — Tower A, applying membrane coat #2. • Interior drywall framing — floors 1–2 common areas and lobby.

Work Performed

• Steel erection crew set 22 tons of structural steel on floors 8–10, north and east bays. All bolted connections torqued and inspected. • Concrete crew poured Level 7 suspended deck — 85 CY of 5000 psi concrete, pump truck from Peach State Concrete Pumping. Pour started at 7:30 AM, finished by 11:45 AM. Finishing and curing compound applied by 1:00 PM. • MEP crews ran electrical conduit (EMT and rigid) through floors 3–5, installed 4 plumbing waste risers and 2 vent stacks in Tower A core. • Curtain wall crew began mullion framing on south elevation floors 2–4. Set 18 mullion sections and 6 transom bars. • Drywall framers completed metal stud layout for lobby walls on floor 1 — 1,200 SF framed. • Elevator pit crew applied second coat of waterproofing membrane in Tower A pit.

Detailed Weather

Morning

Clear, mild humidity

Temp: 72°F

Wind: Calm, 3 mph E

Midday

Partly cloudy, warm

Temp: 85°F

Wind: 6 mph SE

Afternoon

Building cumulus, slight breeze

Temp: 88°F

Wind: 10 mph SE gusting 14

Weather Impact

No weather-related delays or impacts today.

Delays / Impacts (1)

Material Delivery

Curtain wall mullion delivery was 6 units short of PO quantity. Backorder items not available until June 10.

Crew: Curtain wall crew — south elevation above floor 4Responsible: Kawneer (supplier)
Cost: No
Schedule: No
CO: No
Notice: No

Sufficient material on hand to continue south elevation floors 2–4. Shortfall will not impact current week's production. Apex Facade PM contacted Kawneer to expedite remaining 6 mullions. No schedule impact anticipated if delivery arrives by June 10 as promised.

Daily Executive Summary

Productive day across all active work fronts. Steel erection on floors 8–10 is progressing well with 22 tons placed today, and the Level 7 concrete deck pour was completed on schedule (85 CY). Curtain wall installation has officially kicked off on the south elevation which is a key milestone. MEP rough-in continues to track on floors 3–5 with one coordination issue resolved early in the day. The quality inspection on steel connections and concrete met all requirements. Overall the project is at 42% complete with the critical path focused on steel erection recovery and curtain wall procurement. No safety incidents or environmental issues today.

Tomorrow's Plan

• Continue steel erection on floors 9–10, targeting 18 tons. • Begin Level 8 deck forming — install shoring towers and form panels. • MEP to continue conduit and riser work on floors 4–5. • Curtain wall crew to continue mullion installation, south elevation floor 3–4. • Fireproofing crew to begin spray application on floor 5 columns and beams. • Waterproofing crew to mobilize for below-grade parking structure east wall.